Research note: Microsoft pulls out of Nscale’s planned AI data centre in Loughton, Essex, as power delays bite

How we checked Microsoft’s exit from the Loughton project and kept the reason clearly unknown.

At a glance

3searches run
3sources read
2sources used
7facts labelled
Mixedevidence strength · 4 of 6 facts (67%)

How we rate evidence: Some facts are confirmed, others rest on one report or on the company’s own claims. We count the share of known facts labelled Confirmed or Reported: 70% or more is Strong, 40–69% Mixed, below 40% Limited.

From sources to story

How many sources we read, how many we used, and how many are official or archived.

Read3Every source we opened
Used2Relied on for the story
Cited2Linked in the story
Official0From the company or a public body
Archived1Saved on the Internet Archive

How sure we are, fact by fact

  • Reported · 4 — Two or more independent, named outlets say it.
  • Unconfirmed · 2 — One report only, shown with its source.
  • Not known · 1 — Not announced or not answered yet.

Evidence map

Each row is a fact from the story; each column is a source. A filled dot means that source supports the fact.

FactLabel1OUT2OUT
Microsoft withdrew from Nscale’s planned AI data centre in Loughton, Essex, first reported by The Telegraph.Reported
Microsoft declined to comment and gave no reason.Reported
Nscale says its relationship with Microsoft remains strong and other contracts are unaffected.Reported
The site was told enough power may not arrive until the 2030s.Reported
Microsoft had agreed to lease the first 50MW of a site expandable to 90MW.Unconfirmed
Nscale seeks up to $3 billion in its IPO.Unconfirmed
Microsoft’s reason for withdrawing.Not known
Question

What we set out to check

Whether Microsoft has left the project, why, what Nscale said and what happens to the site.

Findings

What we found

  • Both outlets say The Telegraph first reported the withdrawal and that Microsoft declined to comment.
  • Both carry the same Nscale statement.
  • Neither report gives Microsoft’s reason, so we do not suggest one.
Discrepancies

Numbers that differ

TNW says power is not expected “until the 2030s”; CloudComputing News, citing The Guardian, says “early to mid-2030s”. We use the broader phrase.

Method

Labels we chose and why

  • Reported for the withdrawal, statements and grid delay.
  • Unconfirmed for the 50MW lease and IPO size, each seen in one outlet.
Open questions

What we could not verify

  • The Telegraph’s original report, which is behind a paywall.
  • Microsoft’s reason for leaving.

Can you help confirm one of these? Send us a source. When we find an answer, we update this note and the story, with the date.

Next steps

How we could improve this

Check Nscale’s IPO filing directly for the capacity figures and update if Microsoft comments.

Research timeline

  1. Research20 Oct 2026
  2. Research note published20 Oct 2026, 12:27 IST
  3. Story published20 Oct 2026, 12:37 IST

What we searched

  • Microsoft Nscale Essex data centre withdraws
  • Nscale Loughton power 2030s
  • Nscale IPO Microsoft Loughton

Every source we read

SourceUsed?Why
TNW
Archived copy
USEDWithdrawal, Nscale statement, IPO size.
CloudComputing NewsUSEDCapacity, grid timing, filing figures, Ofgem context.
IBTimes UKNOT USEDSimilar summary.

Sources cited in the story

  1. 1TNW: Microsoft reportedly quits Nscale’s UK data centre weeks before its IPOOUTLET
  2. 2CloudComputing News: Microsoft exits UK AI data centre deal amid reported power grid delaysOUTLET

Research notes show our working. They are not peer-reviewed papers. Data: facts as JSON · How we report